California State University San Marcos wanted proposals for a website assessment by October 16. Then it pushed back the date it would post answers to firms' questions and moved the deadline with it. It did that five times in four weeks. Proposals are now due November 20.
That's an extreme case of a common pattern. Our study of 1,040 government Requests for Proposal (RFPs) found that more than one in five changed their terms before the deadline, and more than two-thirds of those moved the deadline. This time we looked only at the deadline moves, made by addendum (a formal change to the RFP) or another notice: 309 of them, on 250 RFPs from state, local, and tribal governments in California, Washington, Oregon, and Idaho, issued between June 25 and November 12, 2026.
What we found
When a deadline moves, it moves later. 294 of the 309 moves added time.
The typical extension is a week. The median is 7 days. 130 of the 294 extensions added exactly 7 or 14 days.
It comes late. Nearly six in ten extensions came in the final week. More than one in four came two days or less before the deadline.
It rarely comes alone. 45% of the filings that moved a deadline changed something else too.
One move often means another. One in six RFPs that moved its deadline moved it again.
Asking works about half the time. Firms asked for more time on 107 RFPs. About half got it, usually a week rather than the two weeks they asked for.
Most RFP deadline extensions add a week, often to the day
The median extension was 7 days. Only six added more than a month. 86 added exactly 7 days and 44 added exactly 14: 130 of 294, or 44%. Someone picks the same weekday, one or two weeks out, and reissues the calendar.

So an extension is real time, but not much of it. A week buys a cleaner draft. It doesn't buy a different proposal.
Extensions are announced in the final week
The median extension was issued 6 days before the deadline it replaced. Nearly six in ten came inside the final week. 78 of 294, more than one in four, came two days or less before it.
25 were issued on the day proposals were due. El Dorado County signed an addendum that morning adding a week. Eight came after the deadline: the Pasco Public Facilities District reposted its executive director RFP three weeks after proposals were due and let firms that had already submitted amend their proposals.

The timing follows from the calendar. When the answers to firms' questions run late, the deadline moves to make room for them. By then, a firm that planned to the printed date has done most of the work.
On RFPGo, an RFP's page shows when its (amended) deadline has moved and what changed. Explore active RFPs →
RFP deadlines get extended for ordinary reasons
Most notices don't say why the deadline moved. None of San Marcos's five addenda did. The ones that give a reason give ordinary ones:
Portals that fail. The City of Spokane extended a deadline twice, two weeks in all, after a technical error in its ProcureWare portal kept firms from opening the RFP.
Notices that didn't go out. The Squaxin Island Tribe added nine days because not every firm on its consultant shortlist had been notified directly.
The calendar. A firm pointed out that Contra Costa County's due date fell on Labor Day, and the County moved it to the next day.
None of those is a sign that the RFP is in trouble. A deadline move is usually housekeeping.
The addendum that extends the deadline often changes other terms
Read the notice that moves the deadline from top to bottom. In 140 of the 309 filings, the same document changed something else:
how to submit: 56
a compliance requirement: 46
the scope or requirements: 33
the pricing: 15
80 of the moves arrived inside a questions-and-answers (Q&A) document rather than a separate addendum. The answers are often where the terms move.
One extension often means another
41 of the 250 RFPs moved their deadline more than once. Two Los Angeles World Airports requests for qualifications (RFQs) went from October 1 to December 4 in four moves each. Pierce County's RFP for jail communication services is on its tenth addendum, which moved proposals to November 18 and called it the final extension.
Earlier deadlines are rare, and they're mostly fixes. Sacramento County's airport RFQ printed October 20 as the deadline in two places and October 13 in a third. When a firm asked, the County said the 13th was right.
The addendum that drops late on a Friday is real, but Friday isn't the usual day. More deadlines moved on Thursdays (76) and Tuesdays (70) than on Fridays (55).
Asking for more time works about half the time
In 107 of the 736 RFPs where we have the published questions and answers, at least one firm asked for more time to submit. Most asked for two weeks.
About half got it. On 49 of those RFPs, the answer was yes, or the deadline moved later after the request. On 47, the government entity said no. A yes usually meant a week: the median first extension after a request was 7 days.
The no's come with reasons from the government entity's calendar: a council meeting the award has to reach, a contract about to expire, a grant deadline. The City of Chula Vista said it had to finish before its current contract expired at the end of the year.
Asking isn't what moves most deadlines, though. Of the 167 RFPs here that moved their deadline and have published answers, 38 show a firm asking first.
What to do about it
Plan to the printed date. Our earlier study found that only 130 of 1,040 RFPs got more time. Treat an extension as found time.
Check again in the final week. That's when most extensions land, along with whatever else changed in the same filing.
Read the whole notice. If you read only the new date, you miss the new submission instructions.
When it moves once, expect it to move again. Keep the draft ready for the new date, not the one you hope comes next.
If you need more time, ask in the question period. Ask for two weeks, plan on one, and keep working to the printed date until an addendum says otherwise.
RFPGo follows every RFP from posting to (amended) deadline. Each RFP's page shows how many times its deadline has moved, the latest old and new dates, and every filing that changed it, labeled by what it changed. Explore active RFPs →
Questions firms ask about RFP deadline extensions
How long is a typical RFP deadline extension? A week. The median was 7 days.
When are RFP deadline extensions announced? Usually in the final week, and more than one in four come two days or less before the deadline.
Can you ask for an RFP deadline extension? Yes, in writing during the question period. About half the requests we tracked got more time, usually a week.
Can an RFP deadline be extended more than once? Yes. One in six RFPs that moved its deadline moved it again.
Can an RFP deadline move earlier? Rarely. 5 of 309 moves pulled a deadline earlier; most were corrections.
Method and sources
Moves: every filing logged against a professional services RFP that changed its due date, issued June 25 to November 12, 2026, as logged that afternoon: addenda, Q&A documents, notices and recalls. We excluded 18 cancellations and counted a repeated announcement once: 309 moves on 250 RFPs. Two with no recorded prior date are excluded from the size and timing figures.
Direction and size: calendar days in Pacific time between the deadline in force and the new one. 294 moves added time, 5 pulled the deadline earlier, and 8 changed only the time of day.
The earlier study: How Often Do Government RFPs Change Their Terms?, 1,040 RFPs due by October 31, 2026 (updated November 13).
Source: RFPGo.ai internal data.